Case Studies, International, News

Full service gets largest Liebherr crane up and running on time

Smart engineering, flexible planning and continuous optimization ensure successful project.

Once reinstalled on the offshore vessel “Orion”, the Liebherr HLC 295000 crane will play an important role in the energy transition by being used in the construction of modern offshore wind turbines. With its first project already scheduled, the top priority was to meet the delivery date for Liebherr’s customer DEME.

Due to the successful initial installation and a convincing full-service package from engineering to supervision, Mammoet again won the client’s trust and the contract for all transport and lifting activities associated with rebuilding the crane. The dimensions of the HLC 295000 components were unusual, to say the least: the slewing unit weighs 1,850t, the boom is 1,500t and 120m long, and the A-frame weighs 900t and 70m long.

Handling these items would require specialist expertise, even by the standards of the heavy lifting industry. With its many engineering nerve centers separate to operational activity and the world’s largest fleet of equipment, Mammoet was able to mobilize the team and equipment to get the job done safely and efficiently.

In fact, to handle these highly specialized items safely, Mammoet needed to deliver around 2,000t of material to the site. This included various cranes, transport vehicles, 400t of rigging equipment, as well as support and special equipment. The rigging alone for lifting the boom weighed 80t.

The plan created by Mammoet’s engineering team was to create a custom transport and lifting concept using Liebherr’s own TCC 78000 rail-mounted heavy-duty crane. The plan would also use two crawler cranes, several mobile cranes and Mammoet’s JS 500 jacking system.

Special rigging schemes were designed and fabricated to meet the specific component requirements. In order to maneuver the oversized and heavy components safely across the Liebherr site, the transports were planned with 68 axle line SPMTs.

First, the slewing unit was transported from the pre-assembly site to the crane location. It was lifted and installed onto the offshore vessel “Orion” in a tandem lift using the TCC 78000 and an LR 11350.

In a second operation, the A-frame was erected via a tandem lift using the TCC 78000 and an LR 1750. The component was transported approx. 800m on the hook of the TCC 78000 and lifted to a height of 120m, onto the “Orion”, for installation.

Finally, the boom was lifted onto the “Orion” in a tandem lift using the TCC 78000 and a LR 1750 to a height of approximately 60m and installed. The LR 1750 crawler crane, which had previously been used to tail the A-frame, was moved from the pre-assembly site to the quay within a very short time and reconfigured to “luffing jib mode” for the boom lift.

“Execution in autumn and winter always brings special challenges for projects of this type. The frequent occurrence of storms was closely monitored by permanently checking and previewing the weather conditions. Thus, even the smallest wind windows could be exploited to safely realize partial activities within the specified time. Even the start of the lifting activities as early as 4 a.m. in the morning posed no obstacle.” explains Gernot Öder, Manager Crane and Transport Projects Engineering & Project Management.

The experienced team reacted flexibly to the constantly changing requirements in operational business and adapted the engineering and lifting plans just in time. Through constant optimization, the ambitious schedule could even be shortened in some cases.

The restored crane’s first project will be “Arcadis Ost” in the Baltic Sea and further deployments are already planned. 

 

Send this to a friend